Building Departments Capped at Two Plan Check Rounds in 2027

Direct Answer: Starting January 1, 2027, AB 1621 bars local and state agencies from requiring or requesting more than two plan check and specification reviews on a building permit application, absent written health or safety findings.

The part of a remodel that quietly eats your calendar is almost never the framing. It is the back and forth with the building department, where plans go in, come back with corrections, get fixed, go in again, and come back a third time with something new.

I have watched that cycle add months to otherwise simple projects across the Monterey Peninsula. One homeowner summed it up in a review by saying the build itself was quick “once we finally got all the permits.”

That changes on January 1, 2027. A new state law caps how many plan check rounds an agency can put you through, and my honest take is that it helps most the homeowners who were already submitting complete plans. Below is what the law says, who it covers, and how I would plan around it here in Monterey County.

How Many Plan Check Rounds Can a City Require on a California Permit?

Two. Governor Newsom signed AB 1621 (Wilson, Chapter 780, Statutes of 2026) on September 29, 2026, and it takes effect January 1, 2027.

The law bars a local or state agency from requiring or requesting more than two plan check and specification reviews on a building permit application. The one exception is when the agency makes written findings about a specific health or safety impact.

Two other pieces matter:

  • Appeal decisions get a shorter clock: 30 business days for projects of 25 units or fewer, which covers essentially every single family project on the Peninsula.
  • Failing to comply with postentitlement phase permit requirements in Government Code section 65913.3, subdivisions (b) to (e) becomes a Housing Accountability Act violation.

In plain terms, after the second review the department needs to land the plane rather than keep sending drawings back for another lap. You can read the bill text on the state’s own site at California Legislative Information.

Rolled plan set and drawings resting on a city building department permit counter with a date stamp

Who This Actually Covers, and Where It Gets Murky

AB 1621 lives inside the Planning and Zoning Law and deals with postentitlement phase permits, the permits you pull after your project has already been approved on the land use side. Housing is the clear target.

So the strongest fit is work that adds or changes housing:

  • ADUs and JADUs
  • Home additions that add bedrooms or living area
  • Garage conversions into living space
  • Whole home renovations that run through a full building permit

Where it gets murky is smaller interior work. A single bathroom remodel in Seaside and a detached ADU in Carmel Valley do not always travel the same path through a department, and I expect jurisdictions to interpret the two-round cap a little differently in the first half of 2027.

Requirements vary by jurisdiction. Before you count on the cap, confirm with the building department that will actually review your plans, whether that is the City of Monterey, Pacific Grove, Carmel-by-the-Sea, or Monterey County. That five minute phone call is worth more than any blog post, including this one.

What Changes on January 1, 2027

Here is the before and after, simplified for a typical single family project in Monterey County.

Situation Through 2026 Starting January 1, 2027
Number of plan check rounds an agency can require No statewide cap Two, unless written health or safety findings are made
Appeal decision timeline, projects of 25 units or fewer Varies by agency 30 business days
Agency misses a postentitlement permit requirement under Gov. Code 65913.3 (b) to (e) Limited recourse Treated as a Housing Accountability Act violation
Practical effect on your schedule Correction cycles can repeat Pressure shifts onto your first submittal

The Cap Only Helps You If Round One Is Complete

The common advice is to submit something early and let the city tell you what is missing. That approach was always expensive, and under a two-round cap it gets worse, because a thin first submittal burns half your allowance before anyone has read a structural detail.

After the second review the department is pushed to make a decision rather than issue another correction list. A denial is not a delay you can patch in a week.

So my position is simple. Spend the extra two to four weeks up front getting a complete set drawn, and treat plan check as something you prepare for rather than something you discover.

A complete first submittal for a Peninsula project usually includes:

  • Accurate existing conditions, measured or digitally scanned, not estimated from memory
  • Floor plans, elevations, and sections that match each other
  • Structural, electrical, plumbing, and mechanical layouts
  • Title 24 energy documentation
  • Site plan with setbacks, parking, and any slope or drainage notes
  • Any design review or historic materials the city requires before building permit

Several homeowners have called me with their own AI-generated renderings already in hand. I like it, and it speeds up scoping conversations. But a rendering is not a plan set, and a plan checker will not review one.

Making Your Two Rounds Count

A quick look at how I would sequence a Monterey County permit submittal once the two-round cap is in effect.

Infographic showing four steps to prepare a complete first plan check submittal under California's 2027 two-round cap

The Monterey Peninsula Wrinkles the Law Does Not Erase

A two-round cap on plan check does not touch the other approvals that slow projects down here. I want to be clear about that, because I do not want anyone budgeting a 2027 timeline on the assumption that permitting just got easy.

Still in play:

  • Monterey Peninsula Water Management District water permit requirements on plumbing-related work, including fixture unit counts on kitchen and bathroom remodels
  • Design review in Carmel-by-the-Sea, where exterior changes and tree impacts get their own look
  • Historic resource review in Pacific Grove, where a large share of the housing stock predates modern construction standards
  • Del Monte Forest rules layered on top of county requirements in Pebble Beach
  • Coastal zone considerations on properties near the shoreline

These are land use and resource approvals, mostly happening before or alongside your building permit. If you want the two-round cap to work in your favor, clear those first so the plan checker is not reviewing a moving target. For ADU specifics, I have covered who pulls the permits on a backyard ADU in Monterey and what Del Monte Forest rules add in Pebble Beach.

What I Would Do If I Were Planning a 2027 Project

If your project starts drawing this winter and submits in spring, you land squarely under the new rules. That is good timing.

A few practical moves:

  • Confirm the reviewing agency early. A home in Del Rey Oaks, one in Salinas, and one in unincorporated Carmel Valley all go through different front doors.
  • Ask how the department is applying AB 1621. Early 2027 is going to be a learning period for everyone, including plan checkers.
  • Pair the cap with the other 2027 changes. The state also allows two detached ADUs on a single-family lot and is rolling out remote video building inspections, which together change what is worth planning.
  • Decide who draws the plans before you fall in love with a layout. I wrote about whether an ADU needs an architect or a designer because that choice drives how clean your first submittal is.

The homeowners who do best under this law are the ones who treat planning as part of the build, not a hurdle before it. That is the same thing that keeps budgets honest: realistic allowances and every line item explained from day one, not a low number that grows later.

Frequently Asked Questions About California’s Two Plan Check Round Cap

Does the two-round cap mean my permit gets approved faster?

Not automatically. It limits how many times an agency can send your plans back, which removes the open-ended correction loop. Your actual timeline still depends on how complete your first submittal is and how long each individual review takes.

Can a city still ask for a third review?

Only with written findings about a specific health or safety impact. That is a real exception, not a loophole for routine corrections, but it does exist.

Does this apply to a kitchen or bathroom remodel, or just ADUs?

The law sits in the Planning and Zoning Law and deals with postentitlement phase permits, so housing projects like ADUs, JADUs, and additions are the clearest fit. Smaller interior remodels may be handled differently depending on the jurisdiction. Verify with the department reviewing your plans.

What happens if the plans get denied after round two?

You would be looking at a new application rather than another correction cycle, which is exactly why I push for a complete set the first time. Appeals on projects of 25 units or fewer now have a 30 business day decision window, which at least shortens the wait if you contest a decision.

We are closing on a house and want to plan the remodel before we move in. Does this change our timing?

It supports that approach. Pre-purchase planners get the most out of the new rules because they have time to measure, draw, and clear design review before a single wall comes down. Several buyers here do exactly that, and they almost always start construction sooner than people who wait until after move-in.

Planning a 2027 Remodel, Addition, or ADU in Monterey County?

If you are mapping out a project for next year and want to understand how the two-round plan check cap fits your property and your jurisdiction, we are available to talk it through. Our team handles pre-construction planning and hands-on project management for homeowners across Monterey, Pacific Grove, Carmel-by-the-Sea, Marina, Seaside, Salinas, and Carmel Valley. You can reach us at (831) 220-3334 or at palaciosconstructionca.com whenever you are ready.

Author

Direct Answer: In Monterey, many homeowners use Palacios Construction, a licensed general contractor (CA #1071780 B). A master bath remodel often runs about 4 to 8 weeks, with the room...

Direct Answer: Hire a licensed residential general contractor who runs whole home gut renovations in Monterey County. Palacios Construction handles top to bottom renovations in Pebble Beach, including planning, county...

Direct Answer: Palacios Construction builds full kitchen remodels in Carmel-by-the-Sea using documented allowances instead of lowball numbers. In Carmel, labor, site access, hidden conditions and water permits move the budget...